2004 Construction Program

[ 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | Index ]


Project: STP-S-C082(29)--5E-82
Location: St. Ann's Road (290th St) From 115Ave (F52) to Pioneer Village
Status: Completed
Construction Time: 103 days
Project Cost: $1,866,480.47
Contractor: Mathy Construction CO.

Description: Construction will include Rubblizing the existing surface, placing a 6inch asphalt overlay and new rock shoulders. Road will be open to traffic, although traffic will be controlled by pilot car, expect delays. Letting on February 17, 2004. Construction will be done in conjunction with construction on South Park Road and McCausland Road. The combined projects should take most of the summer to complete.