2004 Construction Program

[ 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | Index ]


Project: BROS-C082(31)--5F-82
Location: Bridge number 31 Lincoln on 210th St
Status: Completed
Construction Time: 55 days
Project Cost: $217,692.10
Contractor: Muscatine Bridge Co.

Description: Existing 80' by 22' Slab bridge to be replaced with 100' by 30' continuous concrete slab bridge. Letting on February 17, 2004. Road will be closed during construction. Estimate 6 to 8 weeks of construction

31 Lincoln East 31 Lincoln West 31 lincoln East View 31 lincoln North Side 31 lincoln South Side 31 lincoln both piers 31 lincoln both piers encased 31 lincoln driving pile 31 lincoln driving pile 1 31 lincoln ecasements 4 31 lincoln encasements 31 lincoln encasements 1 31 lincoln encasements 3 31 lincoln excavation 31 lincoln piling 31 lincoln piling 1 31 lincoln piling 2 31 lincoln piling leads 31 lincoln removal 31 lincoln removal 2 31 lincoln removal 3 31 lincoln view from road