Project: FM-C082(34)--55-82
Location: South Park Road (270th St)
Status: Completed
Construction Time: 25 days (includes work for FM-C082(28)--55-82)
Project Cost: $201,903.59
Contractor: McCarthy Improvement

Description: This project was tied to Project FM-C082(28)--55-82, the South Park Road The road was rehabilitated using the crack and seat method, 5 Asphalt overlay, and new rock shoulders.