2003 Construction Program

[ 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | Index ]


Project: FM-C082(28)--55-82
Location: F41 Long Grove to Park View (267th St)
Status: Completed
Construction Time: 25 days (includes work for FM-C082(34)--55-82)
Project Cost: $375,432.34
Contractor: McCarthy Improvement

Description: This project was tied to Project FM-C082(34)--55-82, the road from Long Grove to Park View. The road was rehabilitated using the crack and seat method, 5 Asphalt overlay, and new rock shoulders.


2003 Projects: