2002 Construction Program

[ 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | Index ]


Project: BROS-C082(27)--8J-82
Location: Mud Creek Bridge
Status: Completed
Construction Time: 45 days (a little over two Months)
Project Cost: $240,027.12
Contractor: Jim Schroeder Construction

Description: This project consisted of replacement of a 70' by 17' pony truss bridge on 90th Ave over Mud Creek, with a 155.5' by 30' Slab Bridge. The roadway approaching the bridge was raised in order to help prevent flooding. 1800 cubic yards of fill was added to the existing roadway to raise it to its new elevation.

21C Longitudinal upstream 21C looking South

2002 Projects: